Proposed Amendments to DEP Site Remediation - Mandatory and Regulatory Timeframes

In October, the New Jersey Department of Environmental Protection (“DEP”) proposed several amendments to two of its site remediation regulations, the Administrative Requirements for the Remediation of Contaminated Sites (the “ARRCs”) (N.J.A.C. 7:26C) and the Technical Requirements for Site Remediation (N.J.A.C. 7:26E).

There are three primary components to the proposed amendments. The first is to extend the Mandatory and Regulatory Timeframes established under the ARRCs, the second is to clarify the definition of a vapor intrusion immediate environmental concern (“IEC”), and the third addresses timing for receptor evaluation reporting. The proposed rule changes are subject to a 60-day public comment period that expires on December 3, 2010.

Mandatory and Regulatory Timeframes

In revamping the DEP’s site remediation program through its enactment of the Site Remediation Reform Act (see January 6, 2010 post), the legislature required the DEP to enact certain mandatory and regulatory remediation timeframes.  The DEP established certain mandatory and regulatory time frames in the ARRCs. The DEP required responsible parties to undertake the following actions within one year from either March 1, 2010 (for cleanups commenced before November 4, 2009) or a specified triggering event:

  • submit a preliminary assessment report and site investigation report for a cleanup under the Industrial Site Recovery Act
  • submit a site investigation report under the Underground Storage of Hazardous Substances Act
  • submit an initial receptor evaluation
  • complete the delineation of an IEC source area, initiate IEC source control and submit to DEP an IEC Source Control Report
  • complete (i) the installation of a Light Non-Aqueous Phase Liquid (“LNAPL” or “free product”) recovery system, (ii) initial operation monitoring of that system and (iii) submit to DEP an interim remedial action report

The SRRA originally contained a Regulatory Timeframe for an LNAPL recovery system report to be submitted to the DEP within 270 days after free product is identified. Under the proposed Regulatory Timeframe rule change, if free product was identified before March 1, 2010, the free product recovery system report shall be submitted to DEP by March 1, 2011 (extended from 270 days to one year). If free product is identified on or after March 1, 2010, the LNAPL Recovery System Report must be submitted to DEP within one year after discovery.

Under the proposed regulatory amendment, the one-year Mandatory Timeframe deadlines will be extended to two years. If the amendment is enacted, existing cases will have until March 1, 2012 to complete these mandatory requirements. This proposed change would provide significant flexibility to responsible parties, especially given the draconian penalties from failing to meet a Mandatory Timeframe. Those penalties include having the DEP take direct oversight/control of the cleanup and penalties of up to $20,000 per day for a continuing violation.

Note that with respect to the free product requirements, the proposed Regulatory Timeframe deadline will become one year while the Mandatory Timeframe deadline will be extended to two years. The difference relates to the fact that Regulatory Timeframes can be more easily extended than Mandatory Timeframes, which are essentially “drop-dead” deadlines.

Finally, until the amendments are approved and go into effect, responsible parties need to either continue to proceed under the currently enacted deadlines (i.e., one year) or seek approval from the DEP for an extension of the deadlines.

Vapor Intrusion

Vapor intrusion concerns relate to the potential for volatile contaminants to enter building interiors and negatively impact indoor air quality. The DEP has issued guidance for addressing vapor intrusion concerns. In that guidance, DEP has set out a number of indoor air contaminant levels which it defines as “rapid action levels.” These are contaminant levels which require immediate action, including interim remedial measures. The DEP’s proposed rule amendments make clear that an exceedance of the rapid action level for an indoor air contaminant is an IEC, which triggers certain obligations under the state cleanup rules. For instance, interim remedial measures are required within fourteen days of determining that the indoor air exceeds the rapid action level, and is thus an immediate environmental concern.

Receptor Evaluation Reporting

The current rule required a Receptor Evaluation Report to be submitted to the DEP by November 26, 2010. However, the proposed rule states that if remediation was initiated before March 1, 2010, the initial Receptor Evaluation Report must be submitted by March 1, 2011. If remediation is initiated on or after March 1, 2010, the initial receptor evaluation must be submitted within one year of the initiation of remediation. Again, this proposed Regulatory Timeframe changed from 270 days to one year.

NJDEP has issued a Compliance Advisory Update which indicates that they will not take enforcement action against the person responsible for conducting the remediation if they do not meet the regulatory timeframes contained in the current rule as long as they meet the newly proposed regulatory deadlines.

For more information on the proposed amendments to the rules governing site remediation, go to http://www.nj.gov/dep/rules/proposals/100410a.pdf and for a summary of the regulatory and mandatory timeframes go to http://www.nj.gov/dep/srp/srra/training/matrix/new_responsibilities/timeframe_req.pdf.
 

DEP Announces New Office of Dispute Resolution

On September 27, 2010, New Jersey Department of Environmental Protection Commissioner Bob Martin announced the opening of the DEP Office of Dispute Resolution. Commissioner Martin stated that “The Office of Dispute Resolution will play a key role in achieving our goal of breaking down the barriers that have often existed between the DEP and businesses, individuals and local governments.” But the Commissioner warned that “In finding common ground, however, we will not compromise protection of the environment.”

The types of issues which will be appropriate for the dispute resolution process would include, for instance, (a) disputes with the site remediation staff regarding the requirements associated with site cleanups, (b) disputes with the land use permitting staff regarding the issuance of environmental land use permits such as wetland permits and (c) disputes with DEP’s enforcement staff regarding the reasonable amount of penalties, if any, for alleged violations of environmental law.

The alternative dispute resolution process, to be facilitated by the Office of Dispute Resolution, is designed to reduce litigation costs, save time and allow the parties to participate directly in reaching a mutually agreeable resolution of disputes with the DEP. The Office of Dispute Resolution has identified its goals as follows: “define and clarify issues disputed; facilitate communication between regulated parties and DEP staff; encourage collaborative problem-solving; explore options for resolution to the issues; and promote and document a mutually satisfactory agreement.” By participating in the alternative dispute resolution process, parties should be in a position to negotiate with the DEP and reach a resolution of open issues through an expedited process.
 

Getting Heard: When Are Hearings Before the NJDEP or Courts Available?

Every day, the New Jersey Department of Environmental Protection (“NJDEP”) makes many decisions which disappoint the agency’s varied stakeholders. Individuals are upset with NJDEP land use permitting decisions, either because they prevent planned development or allow development on adjacent properties. Permit applicants are upset with limitations placed upon various wastewater or air emissions discharge permits. The ways by which parties may be unhappy with NJDEP decisions are seemingly endless. If a party is aggrieved by an NJDEP decision, what options are there? Go to Court? Seek a hearing before an administrative law judge? This article will explore some of those possibilities.

Hearings Before an Administrative Law Judge

Under the New Jersey Administrative Procedure Act, N.J.S.A. 52:14B-1 et seq. (the “APA”), whether a hearing before an administrative law judge is available depends upon the status of the aggrieved party. Was the petitioning party directly impacted by the NJDEP’s “permit decision” or is the petitioner a third party only indirectly impacted by the agency action? Procedurally, an aggrieved party submits a hearing request to the NJDEP Commissioner’s office. If the Commissioner determines that the petitioner has standing and the request has merit, then the Commissioner will transfer the matter to the Office of Administrative Law to be handled as a contested case before an administrative law judge. A “permit decision” is defined to mean “a decision by a State agency to grant, deny, modify, suspend or revoke any agency license, permit, certificate, approval, chapter, registration or other form of permission required by law ….” N.J.S.A. 52:14B-3.2. This definition is quite broad and would include most, if not all, public agency decisions, including, for instance, those related to land use permits, air or water emissions permits, site remediation decisions, etc.

Where the party wishing to challenge the NJDEP “permit decision” is the party directly involved in, or impacted by, the permit decision, that party has a right to contest the NJDEP “permit decision” through a contested case hearing before an administrative law judge. N.J.S.A. 52:14B-10(c).   The analysis is more complex with respect to the rights of parties other than an applicant to obtain a trial-like administrative hearing. 

The APA declares that state agencies may not promulgate rules which allow third parties to appeal from permitting decisions unless such hearings are authorized by federal or state statute. N.J.S.A. 52:14B-3.1d. Third Parties are defined to include “any person other than: [a.] An applicant for any agency license, permit, certificate, approval, chapter, registration or other form of permission required by law; [b.] A State agency; or [c.] A person who has particularized property interest sufficient to require a hearing on constitutional or statutory grounds.”  N.J.S.A. 52:14B-3.2. 

There are therefore two means by which a third party has a right to an adjudicatory hearing before an agency – either there is specific statutory entitlement to a hearing or Due Process considerations require a hearing. To establish a Due Process right, the party must “demonstrate a particularized property interest of constitutional significance that is directly affected by an agency’s permitting decision.” In re NJPDES Permit No. NJ0025241, 185 N.J. 474, 482 (2006). In NJPDES Permit, the Court noted that “third parties are generally not able to meet the stringent requirements for constitutional standing in respect of an adjudicatory hearing” and that in New Jersey, “there has been legislative recognition of the benefits derived from a rigorous review standard when inquiring into the particularized property interest that generates a third-party hearing right.” Id.

In I/M/O Freshwater Wetlands Statewide General Permits, 185 N.J. 452 (2006), the New Jersey Supreme Court looked at whether adjacent property owners had a right to a hearing to challenge permitting decisions under the Freshwater Wetlands Protection Act. The neighbors asserted that they had standing because the issuance of a wetlands permit could lead to increased flooding on their properties. In ruling that the third parties had no standing, the Court affirmed the lower court’s finding that “the objector’s claim of a particularized constitutional interest in potential worse flooding to their properties was based on pure speculation and added that the local planning board presumably would scrutinize [the developer’s] drainage system to assure that such flooding did not occur. Fear of injury to a property interest … is not a sufficient constitutional basis for an adjudicatory hearing.” I/M/O Freshwater Wetlands 185 N.J. at 461.

In addition to the standing requirements (i.e., a statutory right or a constitutionally recognized property interest), to obtain an administrative hearing a third party must also demonstrate that there are disputed material facts warranting a trial-like administrative hearing. “[A]n evidentiary hearing is mandated only when the proposed administrative action is based upon disputed adjudicatory facts.” Spalt v. New Jersey Dep’t of Envtl. Prot., 237 N.J. Super 206, 212 (App. Div. 1989). As explained in High Horizons Development Company v. Dep’t of Transportation, 120 N.J. 40 (1990), “adjudicative facts have been defined … as facts pertaining to parties and their business and activities. Adjudicative facts usually answer the questions of who did what, where, when, how, why, with what motive or intent; adjudicative facts are roughly the kind of facts that go to a jury in a jury case. In contrast, legislative facts, the determination of which will not normally require a trial-type hearing, do not usually concern the immediate parties, but are the general facts which help the tribunal decide questions of law and policy and discretion.” High Horizons, 120 N.J. at 49-50 (internal quotations omitted).

Disputes Relating to Site Remediation

When disputes arise between the NJDEP and a party conducting a site remediation, there are several options, including a “chain of command” dispute resolution process, an expedited dispute resolution or a proceeding before the Technical Review Panel. 

As set forth in the rules governing “Department Oversight of the Remediation of Contaminated Sites,” N.J.A.C. 7:26C-1.1, et seq., and guidance relating to the Technical Review Panel, the process always involves first trying to reach a resolution with the Case Manager. See e.g., N.J.A.C. 7:26C-1.4(b)-(h). In the “chain of command” approach, if discussions with the Case Manager prove unsuccessful, a written request for dispute resolution can be sent to the Case Manager’s Section Chief. If the requester is not satisfied with the Section Chief’s response, then another written request can be submitted to the applicable Bureau Chief. If that fails, the next written request goes to the applicable Assistant Director, and the next letter then goes to the applicable Director. Finally, the last letter goes to the Director, Assistant Commissioner and Commissioner for resolution. The Commissioner-level decision is required within 21 days of the written request. A response to each of the “preliminary” letters is required within 7 days of the written request. That is the long approach. The NJDEP regulations also establish an expedited review option which circumvents the initial steps and allows for the request for dispute resolution to be submitted directly to the Commissioner. See N.J.A.C. 7:26C-1.4(i). 

If the “chain of command” or expedited review options prove unsuccessful to the party conducting the remediation, that party must go through the NJDEP’s alternative dispute resolution process before the matter will be deemed a contested case and sent by the Commissioner to the Office of Administrative Law for a hearing. See N.J.A.C. 7:26C-1.4(j)-(k). Finally, both the “chain of command” and expedited review options are significantly limited because they do not apply to, among other things, “[t]echnical issues which arise during Department oversight of remediation” or legal issues. See N.J.A.C. 7:26C-1.4(l)2 and 3.

To address technical disputes, the NJDEP has a established a process whereby the NJDEP will assemble an internal “Technical Review Panel” to review the remediation dispute. To obtain a technical panel review of a technical dispute related to a site remediation, the remediating party must first follow a process set forth in the NJDEP’s guidance. See http://www.nj.gov/dep/srp/guidance/techreview/rev_tech_disputes.htm. The first steps towards resolving the dispute are the same as those set forth above. The aggrieved party must first attempt to reach an agreement with the Case Manager, and then the Case Manager’s immediate supervisor. The process continues up the chain of command until the Case Manager’s Bureau Chief determines the issue. If the Bureau Chief’s response/resolution is still unsatisfactory, then the aggrieved party can seek review by the Technical Review Panel. The request for such review must be in writing and directed to the Assistant Commissioner of the Site Remediation and Waste Management program. The request must include a summary of the issue, the history of the attempted dispute resolution and the identification of any applicable deadlines. The party may also request a meeting before the Technical Review Panel. Finally, no new information may be presented in the request.

The Technical Review Panel will not be convened if the dispute (i) involves an enforcement action, (ii) addresses natural resource damage assessments, (iii) relates to a party’s liability for the cleanup or (iv) involves a matter of policy. If a Technical Review Panel is convened, it will consist of three Assistant Director level employees or their designated manager. A designated manager cannot be the Bureau Chief who previously reviewed the dispute. There is no required deadline for the Technical Review Panel to issue its determination.

A review of published Technical Review Panel decisions on the NJDEP’s website indicates that aggrieved parties either prevailed in their claim or, more often, received some change of the NJDEP’s initial requirements (i.e., the disputed requirements) in 35 % of the published cases (5 of 14 cases). It is an open question whether a denial of the requested relief from the Technical Review Panel would be a final agency action from which an appeal to the Appellate Division could be made. Nevertheless, were such an appeal taken, the likelihood of success would be low due to the courts’ general deference to an agency when the subject matter of the dispute falls within an agency’s particular expertise. 

Finally, it is worth noting that the newly passed Licensed Site Professional Bill (see http://www.environmentalandenergylawmonitor.com/tags/licensed-site-professional/), which is expected to be signed into law by Governor Corzine, may change the need for addressing technical disputes regarding site remediation projects. 

Going to Court

Access to the courts to challenge agency decisions generally requires that the petitioner first exhaust all of its administrative remedies. New Jersey Court Rule 2:2-3(a)(2) provides that a litigant may not generally seek appellate review of an administrative decision when “there is available a right of review before any administrative agency or officer, unless the interest of justice requires otherwise.” R. 2:2-3(a)(2). Furthermore, in Abbott v. Burke, 100 N.J. 269 (1985), the New Jersey Supreme Court noted that “[in] general, available and appropriate administrative remedies should be fully explored before judicial action is sanctioned.” Id. at 296.

The Court cited three significant policy reasons for requiring exhaustion of administrative remedies: “(1) the rule ensures that claims will be heard, as a preliminary matter, by a body possessing expertise in the area; (2) administrative exhaustion allows the parties to create a factual record necessary for meaningful appellate review; and (3) the agency decision may satisfy the parties and thus obviate resort to the courts.” Id. at 297-98 (citations omitted).

Yet, the Court also indicated that “the preference for exhaustion of administrative remedies is one of convenience, not an indispensable pre-condition.” Id. 100 at 297 (citations omitted). Nevertheless, it is only in limited circumstances that a court will permit a litigant to circumvent the exhaustion requirement. Those situations include “when the administrative remedies would be futile; when irreparable harm would result; when jurisdiction of the agency is doubtful; or when an overriding public interest calls for a prompt judicial decision.” Id. at 298 (citations omitted). Additionally, the exhaustion doctrine is often inapplicable “when only a question of law need be resolved.” Id. “However, even in cases involving only legal questions, jurisdiction should remain with the agency where the agency is in a special position to interpret its enabling legislation, can conclusively resolve the issue . . . and can provide relief for the plaintiff.” Triano v. Div. of State Lottery, 306 N.J. Super. 114, 122 (App. Div. 1997).

Conclusion

As can be seen, there are many considerations which must be made in determining how to respond to an unfavorable NJDEP determination. Given the court’s and administrative law judges’ general deference to agency expertise, there can be significant hurdles to reversing NJDEP determinations. 

A version of this article appeared in the November 24, 2008 issue of the New Jersey Law Journal.

Enforcement Power of NJDEP Increased

On January 4, 2008, the New Jersey legislature passed the Environmental Enforcement Enhancement Act. This Act enhances the enforcement authority of the New Jersey Department of Environmental Protection (“DEP”) under ten environmental statutes: Waterfront Development Act, Pesticide Control Act of 1971, Wetlands Act of 1970, Freshwater Protection Act, Coastal Area Facility Review Act, Endangered and Nongame Species Conservation Act, Water Supply Management Act, Safe Dam Act, Safe Drinking Water Act, and the Flood Hazard Area Control Act. The Act also amends the DEP enabling statute by clarifying DEP’s authority to inspect facilities, collect samples and copy documents to determine compliance with environmental laws, regulations, permits, and orders.

The Act strengthens the enforcement provisions of the ten statutes listed above and substantially increases the penalties DEP may seek against violators. The Act greatly broadens the enforcement authority of the DEP by authorizing it to issue an order requiring any person to comply, to bring a civil action, to levy a civil administrative penalty, or to petition the attorney general to bring a criminal action if a violation occurs. The amendments are substantial because many statutes prior to the passage of the Act only contained minimal penalties for violators or did not contain any provisions for assessing administrative penalties. For example, the Waterfront Development Act’s previous maximum penalty was $1,000 with an additional fine of $100 for each day the violation continued. As amended the penalty is increased to $25,000 per violation, per day. 

To help ensure compliance with environmental statutes, the Act significantly increases civil and criminal penalties including the following changes: (1) uniformly increases the maximum civil penalty amount to $25,000 per day; (2) authorizes daily penalty assessments for continuing violations; (3) authorizes the recovery of compensatory damages for loss or destruction of natural resources (e.g.-creates authority for DEP to recover natural resource damages, which are money damages from anyone responsible for spills or discharges of hazardous substances); (4) authorizes the DEP to recover reasonable costs incurred by the State in removing or correcting a violation, and to recover all reasonable costs incurred in bringing a civil action, which could be interpreted to mean recovery of attorneys’ fees; and (4) clarifies and in some statutes creates criminal provisions for purposeful, knowing, and reckless violations or falsifications. In addition, the Act broadens the DEP’s authority to compel a property owner to record a deed notice on its property where an alleged violation has occurred, under acts such as the Dam Safety Act or the Flood Hazard Protection Act. Prior to the Act’s passage the DEP only had this authority for a violation of the Freshwater Wetlands Protection Act. In fact, the Act allows DEP to require the recording of such a notice based only upon an allegation prior to adjudication.

With the passage of this Act, DEP has increased its enforcement authority and permits it to seek higher penalties for violations that may have previously been cost effective to commit and new avenues to seek such penalties. Its passage will likely lead to an increase in enforcement actions brought by the DEP.